Biomass HoB 2.5 MW plant Stams / Austria

Project: Biomass HoB plant Stams 2.5 MW
Client:  Fernwärme Stams GmbH
Country: Austria
Period:  1997-1998 implementation, 2007 extension
Services: Project development, tender engineering, permission engineering, detail engineering, monitoring
Function: Team leader, ZT Ortner is also shareholder and operator of the plant since 1997


Technical data: DH net lenght 1.8 km, 5 GWh/yr heat demand